Focus On Water Division
Pay For Performance
Site Progress Summary

Site Name: Farmers Union Coop, Cedar Bluffs
UG# 03280-KAM-1300
Posting Date: Sep 30, 2009
Bid Submittal Deadline: Aug 5, 2009
Contractor Selected: Coranco Great Plains
Bid Price: $173,336.00
Methodology: SVE/AS
Time of Contract: 42 Months

Contract Type: COC and Free Product
Contract Start Date: Sep 30, 2009
Milestones Achieved
1. Start up Dec 21, 2009
2. 25% Reduction Apr 19, 2010
3. 50% Reduction Apr 19, 2010
4. 75% Reduction Oct 21, 2010
5. SSTLs or No Free Product
6. One Year Monitoring Start Date
7. Held SSTLs or No FP No
8. Equipment Removal/Site Restoration/ Final Payment
Warranty Period (if needed)
Date Warranty Period Started Mar 30, 2013
Date SSTLs or no FP Achieved
One Year Monitoring Start Date Mar 30, 2014
Held SSTLs or No FP No
Comments:
Site met the 25, 50 & 75% Free Product reduction milestone's but did not meet the final Free Product milestone at the end of the Contract.