Focus On Water Division
Pay For Performance
Site Progress Summary

Site Name: Miller's Corner
UG# 110193-GH-1400
Posting Date: Mar 15, 2007
Bid Submittal Deadline: Jun 15, 2007
Contractor Selected: Versar
Bid Price: $155,300.00
Methodology: Air Sparge, Aeration
Time of Contract: 36 Months

Contract Type: COC
Contract Start Date: Aug 28, 2007
Milestones Achieved
1. Start up Jul 12, 2010
2. 25% Reduction
3. 50% Reduction
4. 75% Reduction
5. SSTLs or No Free Product
6. One Year Monitoring Start Date
7. Held SSTLs or No FP No
8. Equipment Removal/Site Restoration/ Final Payment
Warranty Period (if needed)
Date Warranty Period Started
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
Held SSTLs or No FP
Comments:
Contract terminated.