Site Progress Summary

Site Name: Gas n Shop Waverly (2)
UG# 08109-JHB-1400
Posting Date: Sep 21, 2011
Bid Submittal Deadline: Mar 4, 2011
Contractor Selected: Twin Rivers Testing
Bid Price: $84,900.00
Methodology: Injection
Time of Contract: 38 Months

Contract Type: COC
Contract Start Date: Sep 20, 2011
Milestones Achieved
1. Start up Sep 20, 2011
2. 25% Reduction Mar 15, 2012
3. 50% Reduction Jul 14, 2015
4. 75% Reduction Jul 14, 2015
5. SSTLs or No Free Product Nov 20, 2015
6. One Year Monitoring Start Date Nov 20, 2015
7. Held SSTLs or No FP Yes
8. Equipment Removal/Site Restoration/ Final Payment
Warranty Period (if needed)
Date Warranty Period Started
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
Held SSTLs or No FP
Comments:
After final monitoring period, site held SSTL's and was approved for closure 9/01/16.