Site Name: Freeds Corner
UG# 021491-JB-1030
Posting Date: Sep 5, 2003
Bid Submittal Deadline: Aug 29, 2003
Contractor Selected: Vesar Inc.
Bid Price: $248,000.00
Methodology: SVE/AS
Time of Contract: 27 Months

Contract Type: COC
Contract Start Date: Oct 28, 2003
Milestones Achieved
1. Start up Jan 17, 2004
2. 25% Reduction Jul 27, 2004
3. 50% Reduction Jul 27, 2004
4. 75% Reduction Jul 27, 2004
5. SSTLs or No Free Product Jul 27, 2004
6. One Year Monitoring Start Date Jul 19, 2004
7. Held SSTLs or No FP Yes
8. Equipment Removal/Site Restoration/ Final Payment Nov 15, 2005
Warranty Period (if needed)
Date Warranty Period Started
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
Held SSTLs or No FP
Comments:
Site Closed