Focus On Water Division
Pay For Performance
Site Progress Summary

Site Name: Unknown, Morrill
UG# 04179-NEW-1000
Posting Date: Sep 30, 2009
Bid Submittal Deadline: Aug 5, 2009
Contractor Selected: LT Environmental
Bid Price: $228,790.00
Methodology: SVE/AS
Time of Contract: 36 months

Contract Type: COC
Contract Start Date: Sep 30, 2009
Milestones Achieved
1. Start up Jan 4, 2010
2. 25% Reduction Mar 16, 2011
3. 50% Reduction Mar 16, 2011
4. 75% Reduction Mar 16, 2011
5. SSTLs or No Free Product
6. One Year Monitoring Start Date Jan 24, 2012
7. Held SSTLs or No FP
8. Equipment Removal/Site Restoration/ Final Payment
Warranty Period (if needed)
Date Warranty Period Started Jan 4, 2013
Date SSTLs or no FP Achieved
One Year Monitoring Start Date Jan 4, 2014
Held SSTLs or No FP Yes
Comments:
SSTL's met. Site closed.