Focus On Water Division
Pay For Performance
Site Progress Summary

Site Name: Riteway 81
UG# 07270-KAM-1400
Posting Date: Nov 20, 2002
Bid Submittal Deadline: Jan 24, 2003
Contractor Selected: The Phoenix Group
Bid Price: $424,879.00
Methodology: SVE/AS
Time of Contract: 36 Months

Contract Type: COC
Contract Start Date: Apr 29, 2003
Milestones Achieved
1. Start up May 15, 2003
2. 25% Reduction Oct 4, 2005
3. 50% Reduction Oct 4, 2005
4. 75% Reduction Oct 4, 2005
5. SSTLs or No Free Product
6. One Year Monitoring Start Date
7. Held SSTLs or No FP No
8. Equipment Removal/Site Restoration/ Final Payment
Warranty Period (if needed)
Date Warranty Period Started Apr 29, 2006
Date SSTLs or no FP Achieved Apr 29, 2007
One Year Monitoring Start Date Apr 29, 2007
Held SSTLs or No FP No
Comments:
One well exceed SSTLs by 63 ppb. NDEQ will finish the site.