Focus On Water Division
Pay For Performance
Site Progress Summary

Site Name: Waterloo Gas Mart
UG# 061899-GW-0900
Posting Date: Sep 30, 2009
Bid Submittal Deadline: Aug 5, 2009
Contractor Selected: Coranco Great Plains
Bid Price: $96,781.00
Methodology: SVE
Time of Contract: 24 Months

Contract Type: Free Product
Contract Start Date: Sep 30, 2009
Milestones Achieved
1. Start up Dec 7, 2009
2. 25% Reduction Jan 1, 2010
3. 50% Reduction Mar 16, 2010
4. 75% Reduction Mar 16, 2010
5. SSTLs or No Free Product Mar 16, 2010
6. One Year Monitoring Start Date Sep 30, 2011
7. Held SSTLs or No FP Blank
8. Equipment Removal/Site Restoration/ Final Payment
Warranty Period (if needed)
Date Warranty Period Started
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
Held SSTLs or No FP No
Comments:
Soil vapor concentrations were above SSTLs at the end of the Contract.