Focus On Water Division
Pay For Performance
Site Progress Summary

Site Name: Deyke Oil
UG# 081693-JF-0000
Posting Date: May 19, 2005
Bid Submittal Deadline: Dec 3, 2004
Contractor Selected: Bluestem Environmental
Bid Price: $144,950.00
Methodology: SVE/AS
Time of Contract: 24 Months

Contract Type: COC and Free Product
Contract Start Date: May 18, 2005
Milestones Achieved
1. Start up Oct 11, 2005
2. 25% Reduction Sep 15, 2006
3. 50% Reduction Oct 15, 2006
4. 75% Reduction Oct 15, 2006
5. SSTLs or No Free Product Jan 8, 2007
6. One Year Monitoring Start Date Jan 26, 2007
7. Held SSTLs or No FP Yes
8. Equipment Removal/Site Restoration/ Final Payment Apr 1, 2008
Warranty Period (if needed)
Date Warranty Period Started
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
Held SSTLs or No FP
Comments: