Focus On Water Division
Pay For Performance
Site Progress Summary

Site Name: L & N Service
UG# 072992-EL-1100
Posting Date: Nov 20, 2002
Bid Submittal Deadline: Jan 24, 2003
Contractor Selected: Bluestem Env.
Bid Price: $384,000.00
Methodology: SVE/AS
Time of Contract: 28 Months

Contract Type: COC and Free Product
Contract Start Date: Apr 21, 2003
Milestones Achieved
1. Start up Aug 6, 2003
2. 25% Reduction Nov 3, 2003
3. 50% Reduction Nov 3, 2003
4. 75% Reduction Nov 3, 2003
5. SSTLs or No Free Product Aug 21, 2005
6. One Year Monitoring Start Date Aug 21, 2005
7. Held SSTLs or No FP No
8. Equipment Removal/Site Restoration/ Final Payment
Warranty Period (if needed)
Date Warranty Period Started Nov 17, 2005
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
Held SSTLs or No FP No
Comments:
Site failed for two monitor wells at the end of the warranty period. NDEQ will finish the remediation.