Focus On Water Division
Pay For Performance
Site Progress Summary

Site Name: Jacks Quick Shop
UG# 060393-PH-1345
Posting Date: Nov 20, 2002
Bid Submittal Deadline: Jan 24, 2003
Contractor Selected: Bluestem Env.
Bid Price: $184,000.00
Methodology: SVE/AS
Time of Contract: 28 Months

Contract Type: COC
Contract Start Date: Apr 21, 2003
Milestones Achieved
1. Start up Jul 10, 2003
2. 25% Reduction Sep 12, 2003
3. 50% Reduction Sep 12, 2003
4. 75% Reduction Sep 12, 2003
5. SSTLs or No Free Product Sep 12, 2003
6. One Year Monitoring Start Date Apr 4, 2005
7. Held SSTLs or No FP No
8. Equipment Removal/Site Restoration/ Final Payment
Warranty Period (if needed)
Date Warranty Period Started Aug 21, 2005
Date SSTLs or no FP Achieved Apr 21, 2005
One Year Monitoring Start Date Apr 10, 2007
Held SSTLs or No FP No
Comments:
Site did not hold SSTLs for one monitor well during the final monitoring period. NDEQ will finish the remediation at the site.