Site Name: M&H Oil
UG# 072099-CT-1000
Posting Date: Apr 15, 2005
Bid Submittal Deadline: Dec 3, 2004
Contractor Selected: MILCO
Bid Price: $122,944.00
Methodology: Remedial Excavation
Time of Contract: 24 Months

Contract Type: Free Product
Contract Start Date: Apr 14, 2005
Milestones Achieved
1. Start up Sep 19, 2005
2. 25% Reduction Feb 16, 2006
3. 50% Reduction Feb 16, 2006
4. 75% Reduction Feb 16, 2006
5. SSTLs or No Free Product Feb 1, 2006
6. One Year Monitoring Start Date Feb 1, 2006
7. Held SSTLs or No FP Yes
8. Equipment Removal/Site Restoration/ Final Payment Apr 16, 2007
Warranty Period (if needed)
Date Warranty Period Started
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
Held SSTLs or No FP
Comments:
Site Closed