Site Name: Jaixen's Service
UG# 091694-TH-1327
Posting Date: Aug 31, 2010
Bid Submittal Deadline: Mar 4, 2011
Contractor Selected: Twin Rivers Testing
Bid Price: $92,000.00
Methodology: Over Ex. & SVE
Time of Contract: 30 Months

Contract Type: Soil Vapor
Contract Start Date: Apr 4, 2011
Milestones Achieved
1. Start up May 2, 2011
2. 25% Reduction Jun 2, 2011
3. 50% Reduction Jun 2, 2011
4. 75% Reduction Jun 2, 2011
5. SSTLs or No Free Product
6. One Year Monitoring Start Date
7. Held SSTLs or No FP Yes
8. Equipment Removal/Site Restoration/ Final Payment Nov 12, 2014
Warranty Period (if needed)
Date Warranty Period Started Oct 4, 2013
Date SSTLs or no FP Achieved Oct 9, 2014
One Year Monitoring Start Date
Held SSTLs or No FP Yes
Comments:
Site met all SSTL's for vapor. Final payment made and the Contract closed.