Focus On Water Division
Pay For Performance
Site Progress Summary

Site Name: Brewster Oil
UG# 080995-JB-1730
Posting Date: Mar 15, 2007
Bid Submittal Deadline: Jun 15, 2007
Contractor Selected: SCS
Bid Price: $133,000.00
Methodology: Overexcavation
Time of Contract: 18 Months

Contract Type: COC and Free Product
Contract Start Date: Sep 20, 2007
Milestones Achieved
1. Start up Oct 28, 2008
2. 25% Reduction Feb 3, 2009
3. 50% Reduction Feb 3, 2009
4. 75% Reduction Feb 3, 2009
5. SSTLs or No Free Product Feb 3, 2009
6. One Year Monitoring Start Date Mar 20, 2011
7. Held SSTLs or No FP
8. Equipment Removal/Site Restoration/ Final Payment
Warranty Period (if needed)
Date Warranty Period Started
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
Held SSTLs or No FP No
Comments:
One well failed SSTL's at the end of the monitoring period.