Focus On Water Division
Pay For Performance
Site Progress Summary

Site Name: Bill's Bait & Tackle
UG# 110294-NM-0815
Posting Date: Mar 10, 2006
Bid Submittal Deadline: May 5, 2006
Contractor Selected: MILCO
Bid Price: 129,300.00
Methodology: Overexcavation
Time of Contract: 20 Months

Contract Type: COC
Contract Start Date: Jul 25, 2006
Milestones Achieved
1. Start up Oct 24, 2006
2. 25% Reduction Oct 24, 2006
3. 50% Reduction Oct 24, 2006
4. 75% Reduction Oct 24, 2006
5. SSTLs or No Free Product
6. One Year Monitoring Start Date
7. Held SSTLs or No FP No
8. Equipment Removal/Site Restoration/ Final Payment
Warranty Period (if needed)
Date Warranty Period Started Mar 25, 2008
Date SSTLs or no FP Achieved Mar 2, 2010
One Year Monitoring Start Date Mar 2, 2010
Held SSTLs or No FP No
Comments:
Site had one monitor well that did not meet SSTLs at the end of the monitoring period. DEQ will finish the cleanup.