Focus On Water Division
Pay For Performance
Site Progress Summary

Site Name: Lewellen Conoco
UG# 01199-NEW-1430
Posting Date: Nov 20, 2002
Bid Submittal Deadline: Jan 24, 2003
Contractor Selected: Panhandle Geo. & Env.
Bid Price: $280,809.00
Methodology: SVE/AS
Time of Contract: 36 Months

Contract Type: COC
Contract Start Date: Jun 27, 2003
Milestones Achieved
1. Start up Aug 6, 2003
2. 25% Reduction Feb 13, 2004
3. 50% Reduction Feb 13, 2004
4. 75% Reduction Apr 12, 2005
5. SSTLs or No Free Product Feb 1, 2006
6. One Year Monitoring Start Date Feb 1, 2006
7. Held SSTLs or No FP No
8. Equipment Removal/Site Restoration/ Final Payment Apr 14, 2009
Warranty Period (if needed)
Date Warranty Period Started Feb 1, 2007
Date SSTLs or no FP Achieved Mar 15, 2008
One Year Monitoring Start Date Mar 15, 2008
Held SSTLs or No FP Yes
Comments:
Site held SSTLs. Contract terms met.