Site Name: Seger Oil
UG# 09297-NEW-1400
Posting Date: May 19, 2005
Bid Submittal Deadline: Dec 3, 2004
Contractor Selected: Bluestem Environmental
Bid Price: $189,500.00
Methodology: SVE/AS
Time of Contract: 24 Months

Contract Type: COC
Contract Start Date: May 18, 2005
Milestones Achieved
1. Start up Oct 11, 2005
2. 25% Reduction Feb 16, 2006
3. 50% Reduction Feb 16, 2006
4. 75% Reduction Feb 16, 2006
5. SSTLs or No Free Product Jul 2, 2007
6. One Year Monitoring Start Date Jul 2, 2007
7. Held SSTLs or No FP Yes
8. Equipment Removal/Site Restoration/ Final Payment Dec 1, 2008
Warranty Period (if needed)
Date Warranty Period Started May 18, 2007
Date SSTLs or no FP Achieved Jul 2, 2007
One Year Monitoring Start Date Jul 2, 2007
Held SSTLs or No FP Yes
Comments:
Site met SSTLs and closed