Date: |
3/9/09 |
Site Name: |
Waterloo Gas Mart |
UG# |
061899-GW-0900 |
Address: |
302 Third St. |
County: |
Douglas |
Closest Town |
Waterloo |
Legal Description: |
NE SE NW S10, T15N, R10E |
Contractor Performing Assessment: |
rdg |
Tier 1 Date: |
2/3/04 |
Tier 2 Date: |
4/11/05 |
Property Owner’s Name: |
Marty Stouffer |
Property Owner’s Phone Number: |
402-502-1218 |
Contamination Types: |
Gasoline, Diesel |
PFP Bid Number: |
NE-030 |
Posting Date: |
6/2/09 |
Closing Date for requesting clarifications from the NDEE: |
6/30/09 |
Clarifications to relevant qustions will be issued by the NDEE by: |
7/10/09 |
|
|
Bid Submittal Deadline 8/5/09 at 2:00 pm central time. |
|
|
Site Summary:
This site is located along the Platte River in Douglas County. Ground water averages about 12 feet below the surface, and this remediation will be for free product cleanup. Additionally the site will have a SSTL for soil vapor. NDEQ became aware of this site in 1999 due to closure of seven UST's. The site status was changed to "orphan" in 2000 and the site was activated in 2003. During the Tier 2 investigation, free product was detected in September of 2005. |
|
|
Table 1. Final Tier 2 Sampling Results:
Well | Thickness of Free Product |
MW-4 | .24 |
EW-1 | .02 |
Measured 3/5/09
|
|
|
Table 2. SSTLs:
The SSTLs for this site are removal of free product to less than 0.01 foot. This also applies to all wells surrounding the current free product plume or any wells drilled for verification purposes. There is also a soil vapor SSTL level of no higher than 2,539 mg/m3 benzene, to be verified with direct push technology inside the defined soil cleanup area (see map "soil cleanup area.pdf") This site will have a two year monitoring period.
|
|
|
Pictures:
(See attached file: Gas Mart Pictures 001.jpg)(See attached file: Gas Mart Pictures 003.jpg)(See attached file: Gas Mart Pictures 004.jpg)(See attached file: Gas Mart Pictures 005.jpg)
|
|
|
MAPS: |
Area
(See attached file: Legal Survey Map.pdf)(See attached file: Groundwater Contour.pdf) (See attached file: Soil Cleanup Area.pdf)
|
Benzene Contour
(See attached file: Benzene GW Iscon.pdf)(See attached file: Benzene Isocon 3-5-09.pdf)(See attached file: Benzene Vapor 3-Feet.pdf)(See attached file: Benzene Vapor 8-Feet.pdf) |
|
|
Site Specifications:
1. Please note that other on-site monitor wells have had free product present in the past.
2. The Contract payments for this site are as follows. 1. 40% system installation and operational. 2. 30% no free product present. 3. 30% final payment at the end of the monitoring period (two years).
3. Be aware that this project will be funded wholly or partially with funds from the American Recovery and Reinvestment Act (ARRA). This means that additional terms and conditions will likely be added to the contract. An addendum to this announcement will be provided a minimum of one week prior to the bid submittal deadline with further explanation.
4. The contractor that wins the bid for this project may be required to obtain a registration from CCR (Central Contractor Registration), a government-wide registry for those doing business with the federal government. An addendum to this announcement will be provided a minimum of one week prior to the bid submittal deadline with further explanation. |
|
|
Site Questions and Answers:
|