Air Construction Permit Fee

Must accompany each application for an air quality construction permit, which are based on the potential amount of the facility’s emissions.

What it is:
Each application for an air quality construction permit must be accompanied by a fee in accordance with the schedule shown below. The schedule is based on the facility-wide potential to emit.

Construction Permit Fee Schedule


FACILITY-WIDE Potential Emissions
FEE
Less than 50 tons per year of any single regulated air pollutant (excluding HAPs); or
Less than 2.5 tons per year of any single hazardous air pollutant (HAP); or
Less than 10 tons per year of any combination of HAPs
$250
50 tons or more but less than 100 tons per year of any single regulated air pollutant (excluding HAPs); or
2.5 tons or more but less than 10 tons per year of any single HAP; or
10 tons or more but less than 25 tons per year of any combination of HAPs
$1,500
100 tons or more per year of any single air pollutant (excluding HAPs); or
10 tons or more per year of any single HAP; or
25 tons or more per year of any combination of HAPs
$3,000

How the fee is used:
This fee supplements a small portion of the total costs of the construction permitting program. A
Construction Permit Application Fees fact sheet will provide additional information.

Applicable Regulations: Title 129 – Chapter 17 – Construction Permits

Forms: (none)