Nebraska Department of Environmental Quality
Pay For Performance
Site Progress Summary
Site Name:
Deyke Oil
UG#
081693-JF-0000
Posting Date:
05/19/2005
Bid Submittal Deadline:
12/03/2004
Contractor Selected:
Bluestem Environmental
Bid Price:
$144,950.00
Methodology:
SVE/AS
Time of Contract:
24 Months
.
Contract Type:
COC and Free Product
.
Contract Start Date:
05/18/2005
.
Milestones Achieved
1.
Start up
10/11/2005
2.
25% Reduction
09/15/2006
3.
50% Reduction
10/15/2006
4.
75% Reduction
10/15/2006
5.
SSTLs or No Free Product
01/08/2007
6.
One Year Monitoring Start Date
01/26/2007
7.
Held SSTLs or No FP
Yes
8.
Equipment Removal/Site Restoration/ Final Payment
04/01/2008
.
Warranty Period
(if needed)
Date Warranty Period Started
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
Held SSTLs or No FP
.
Comments:
Department Contacts:
Phil Hargis and David Chambers at (402) 471-3150
For a complete copy of the file,
please follow the copying instructions on NDEQ’s PFP web site.
DEQ.NE.Gov Home Page
Security, Privacy & Accessibility Policy
Nebraska.gov
Nebraska Department of Environmental Quality
1200 "N" Street, Suite 400
P.O. Box 98922
Lincoln, Nebraska 68509
(402) 471-2186