Nebraska Department of Environmental Quality
Pay For Performance
Site Summary

Intended for use by NDEQ's pre-qualified Pay for Performance Contractors. Potential bidding Contractors should not contact the State Contractor that performed the Tier 1 & 2 with questions about the site. Those types of questions should be addressed to Phil Hargis at (402) 471-3150 or Email at Phil.Hargis@Nebraska.Gov.
.
Date:03/09/2009
Site Name:Waterloo Gas Mart
UG#061899-GW-0900
Address:302 Third St.
County:Douglas
Closest TownWaterloo
Legal Description:NE SE NW S10, T15N, R10E
Contractor Performing Assessment:rdg
Tier 1 Date:02/03/2004
Tier 2 Date:04/11/2005
Property Owner’s Name:Marty Stouffer
Property Owner’s Phone Number:402-502-1218
Contamination Types:Gasoline, Diesel
PFP Bid Number:NE-030
Posting Date:06/02/2009
Closing Date for requesting clarifications from the NDEQ:06/30/2009
Clarifications to relevant questions will be issued by the NDEQ by:07/10/2009
Bid Submittal Deadline 08/05/2009 at 2:00 pm central time.

Site Summary:
This site is located along the Platte River in Douglas County. Ground water averages about 12 feet below the surface, and this remediation will be for free product cleanup. Additionally the site will have a SSTL for soil vapor. NDEQ became aware of this site in 1999 due to closure of seven UST's. The site status was changed to "orphan" in 2000 and the site was activated in 2003. During the Tier 2 investigation, free product was detected in September of 2005.

Table 1. Final Tier 2 Sampling Results:


Well
Thickness of Free Product
MW-4
.24
EW-1
.02

Measured 3/5/09

Table 2. SSTLs:
The SSTLs for this site are removal of free product to less than 0.01 foot. This also applies to all wells surrounding the current free product plume or any wells drilled for verification purposes. There is also a soil vapor SSTL level of no higher than 2,539 mg/m3 benzene, to be verified with direct push technology inside the defined soil cleanup area (see map "soil cleanup area.pdf") This site will have a two year monitoring period.


Pictures:
Gas Mart Pictures 001.jpgGas Mart Pictures 003.jpgGas Mart Pictures 004.jpgGas Mart Pictures 005.jpg
MAPS:
Area

Legal Survey Map.pdfGroundwater Contour.pdf Soil Cleanup Area.pdf
Benzene Contour

Benzene GW Iscon.pdfBenzene Isocon 3-5-09.pdfBenzene Vapor 3-Feet.pdfBenzene Vapor 8-Feet.pdf

Site Specifications:
1. Please note that other on-site monitor wells have had free product present in the past.

2. The Contract payments for this site are as follows. 1. 40% system installation and operational. 2. 30% no free product present. 3. 30% final payment at the end of the monitoring period (two years).

3. Be aware that this project will be funded wholly or partially with funds from the American Recovery and Reinvestment Act (ARRA). This means that additional terms and conditions will likely be added to the contract. An addendum to this announcement will be provided a minimum of one week prior to the bid submittal deadline with further explanation.

4. The contractor that wins the bid for this project may be required to obtain a registration from CCR (Central Contractor Registration), a government-wide registry for those doing business with the federal government. An addendum to this announcement will be provided a minimum of one week prior to the bid submittal deadline with further explanation.
.
Department Contacts: Phil Hargis and David Chambers at (402) 471-3150

For a complete copy of the file, please follow the copying instructions on NDEQ’s PFP web site.




Nebraska Department of Environmental Quality
1200 "N" Street, Suite 400
P.O. Box 98922
Lincoln, Nebraska 68509
(402) 471-2186